Tuesday, July 31, 2012

The pouring of the forms is getting closer....


Thursday, July 26, 2012

Due to the rain, the pouring of the footings will occur possibly Friday otherwise next week.

Thursday, July 19, 2012

New helipad taking shape and digging of footings.


Tuesday, July 17, 2012

The concrete pouring of the footings is expected to take place the week of July 23rd and the pouring of the new helipad the week of August 6th.

Wednesday, July 11, 2012

* New electrical lines have been brought in.

* Storm sewers have been completed.

*Upgrades to the propane tank have been completed.