New Pharmacy is completed!!
Monday, October 15, 2012
Monday, September 24, 2012
Monday, September 10, 2012
Hospital Entrance
The hospital entrance on the south side of the building is temporarily inaccessible. Please use the emergency room entrance until further notice.
Monday, August 27, 2012
Tuesday, August 21, 2012
Thursday, August 9, 2012
Friday, August 3, 2012
Thursday, July 26, 2012
Tuesday, July 17, 2012
Wednesday, July 11, 2012
Thursday, June 28, 2012
Wednesday, June 27, 2012
June 25
Beginning to dig! The Storm sewer connections are the first thing to begin. I'm just glad we didn't have open holes when all that rain came! By the end of this week, the demolition of the current helipad should begin. As an alternative for emergency helicopter transport, the Lifelink helicopter service will be landing at the Cook Airport and the Cook Ambulance service will be transporting both the flight crews and patients as necessary between the hospital and the airport.
This process should be in place for about 1 1/2 months. Then back to the Cook hospital. We want to thank Representative Cravaack for his help in moving the process along to get FAA recommendations allowing us to start.
Beginning to dig! The Storm sewer connections are the first thing to begin. I'm just glad we didn't have open holes when all that rain came! By the end of this week, the demolition of the current helipad should begin. As an alternative for emergency helicopter transport, the Lifelink helicopter service will be landing at the Cook Airport and the Cook Ambulance service will be transporting both the flight crews and patients as necessary between the hospital and the airport.
This process should be in place for about 1 1/2 months. Then back to the Cook hospital. We want to thank Representative Cravaack for his help in moving the process along to get FAA recommendations allowing us to start.
Tuesday, June 19, 2012
The storm structures are now approved and ordered and will be delivered Thursday 6/21/12. Schedule as follows,
Mesabi will be starting storm work on 5th Street just south of the church. Working north they will be at the hospital drive Friday 6/22/12 - Monday 6/25/12. Working east along the hospital drive to the connection south of the helipad. This portion should finish by Monday 6/25/12.
Helipad demo will start Tuesday 6/26/12 - Wednesday 6/27/12. Followed by 2 more days of storm work Thursday 6/28/12 and Friday 6/29/12.
Addition excavation Monday 7/2/12-Tuesday 7/3/12.
Schedule could change with weather conditions and unforeseen soil conditions.
Thursday, June 14, 2012
Subscribe to:
Posts (Atom)