The storm structures are now approved and ordered and will be delivered Thursday 6/21/12. Schedule as follows,
Mesabi will be starting storm work on 5th Street just south of the church. Working north they will be at the hospital drive Friday 6/22/12 - Monday 6/25/12. Working east along the hospital drive to the connection south of the helipad. This portion should finish by Monday 6/25/12.
Helipad demo will start Tuesday 6/26/12 - Wednesday 6/27/12. Followed by 2 more days of storm work Thursday 6/28/12 and Friday 6/29/12.
Addition excavation Monday 7/2/12-Tuesday 7/3/12.
Schedule could change with weather conditions and unforeseen soil conditions.